Risk of a ‘bridge to nowhere’ effect in Africa’s electrification

Solar

Risk of a ‘bridge to nowhere’ effect in Africa’s electrification



A report from the United States’ Rocky Mountain Institute finds more work is needed on the demand side for microgrids and other rural electrification projects in Africa. Such projects, says the report, often focus on building generation capacity, with little consideration for the ability of end users to make good use of energy.

The Rocky Mountain Institute (RMI) has published a report evaluating electrification projects in Africa; and concluded schemes are placing too much focus on building generation capacity without consideration for the end use of electricity.

The report’s authors make recommendations to stimulate demand and improve the profitability and effectiveness of such projects.

The study, Closing the Circuit, Stimulating End-Use for Rural Electrification, says publication is a call to action for a more holistic approach to electrification in sub-Saharan Africa. It estimates between 2000 and 2008, close to half the investment in energy access approved by the World Bank went to supply expansion, with just 0.7% directed to the productive use of energy.

“Building megawatts of new generation supply, extending that supply’s reach through transmission and distribution expansion, and growing access to supply via the number of customer connections, risk being a ‘bridge to nowhere’,” states the report. “Although building supply is necessary, assuming that providing supply will generate demand, fails to address the demand-side barriers end-users face.”

Low utilization means high costs and lower demand

The institute notes, without projects to promote end use – such as financing water pumps for farming, or other equipment to increase productivity using electricity – energy systems end up with lower capacity utilization. That leads to an higher cost per kWh for users, reducing demand further.

Comparing electrification in Africa to earlier projects in Europe and the United States, the report notes successful rapid electrification programs historically involved measures to ensure systems had sufficient demand to be financially viable, and to ensure electricity supply would meet needs.

The authors recommend development partners take better consideration of demand for rural electrification, and offer four broad suggestions: developing financing mechanisms to help businesses fund equipment to save labor or switch from diesel; reducing power costs by ensuring mini-grids are an appropriate size and signing contracts with larger customers before designing systems; stimulating private sector sales of electric equipment through customer education, financial guarantees etc; and updating electrification policies to give as much weight to demand considerations as capacity expansion.

Developers can help drive demand

Using a project in Tanzania as an example, the report describes developer JUMEME Rural Power Supply, which was struggling with low utilization, due to unaffordable prices for the power generated by a mini-grid in the Mwanza region. The developer then provided equipment loans to businesses – which it says are due to be repaid on time – and started a business freezing and delivering fish, which improved capacity utilization and provided an additional revenue stream.

Anecdotal examples of such end use considerations creating sustainable business models are plentiful, however the RMI report notes more research is necessary to understand how consumers make decisions and which barriers have the biggest effect on consumption.



Source PV Magazine

Click to comment

Leave a Reply

Your email address will not be published. Required fields are marked *

More in Solar

Categories

October 2018
M T W T F S S
« Sep   Nov »
1234567
891011121314
15161718192021
22232425262728
293031  

Follow

Subscribe to notifications
To Top
%d bloggers like this: