Poland: solar sees bidding prices slightly increase in simulated RE tenders

Solar

Poland: solar sees bidding prices slightly increase in simulated RE tenders



A simulation of Poland’s two upcoming mixed wind/solar auctions held by the Polish wind energy association has shown that wind may prove more competitive than solar, especially in the auction for projects over 1 MW. The real auctions are expected to be launched between November and December.

A simulation of the upcoming tenders for wind and solar projects in Poland, conducted by the Polish Wind Energy Association, PwC and the law firm K&L Gates, has shown that bids for solar projects are slightly higher than those submitted in the country’s previous two renewable energy tenders.

According to local PV analyst Piotr Pająk, the simulation has shown that, in the auction basket for wind and solar projects exceeding 1 MW, the maximum bidding price was 292 PLN ($79.2)/MWh, while maximum bidding price for the auction basket for wind and solar up to 1 MW was 380 PLN ($103.0)/MWh. Furthermore, Pająk has revealed that minimum and maximum prices for solar in both auction baskets were 350 PLN ($94.9) and 411 PLN ($111.4)/MWh, respectively, while minimum and maximum prices for wind were quite lower at 225 PLN ($61.0) and 350 PLN ($94.9)/MWh, respectively.

A comparison is only possible with the previous two mixed solar-wind tenders held by the Polish government, which were devoted only to projects up to 1 MW, and were dominated by solar. In the first auction, 84 offers with a combined capacity of around 70 MW were submitted, while bidding prices ranged from 254 PLN to 409 PLN/MWh. In the second auction there were some 352 winning projects totaling approximately 300 MW, with prices ranging between 195 PLN and 399 PLN/MWh.

For both categories, real auctions should be held somewhere between November and December, according to Pająk. The auction for wind and solar projects over 1 MW, which may see the allocation of around 750 MW of capacity, will make available 45 TWh of energy for a maximum budget of 15,75 billion PLN, while that for projects up to 1 MW will have a budget of 6.2 billion PLN, while making available 16 TWh of energy.

“As for auctions dedicated to projects bigger than 1 MW, wind is still most competitive and should embrace all support in 2018 auction,” Pająk told pv magazine. “However the restrictions in development of new wind projects were implemented into Polish law in 2016, and since then there are no new wind projects being developed,” he also explained. This lack of new wind projects may also do some room for bigger PV projects in next auctions for projects exceeding 1 MW, according to him.

The government and Polish electricity system operator PSE recently said there is a need in the country’s electricity system for around 2 GW of photovoltaics, that should help tackling summer peaks.

According to a recent report from Polish research institute Instytut Energetyki Odnawialnej (IEO), there are currently around 2.1 GW of large-scale PV projects with grid-connection approval in Poland that could potentially compete in the upcoming auctions. Poland’s state-owned utility Polska Grupa Energetyczna (PGE) has so far released the largest number of grid approvals for 942 PV projects with a combined capacity of around 780 MW, which accounts for approximately 45% of the approved capacity. The other power providers Energa, Enea and Tauron accounted for the remaining 23%, 20% and 12%, respectively.

Most of these approved projects – around 1.34 GW – are represents by projects ranging from 500 kW to 1 MW, while projects up to 200 kW and with a capacity between from 200 kW and 500 kW account for 349 MW and 210 MW, respectively. This means that a total of almost 1.9 GW is from projects that can compete in auctions for PV up to 1 MW. Furthermore, the IEO reveals, there is another 179 MW for projects ranging in power from 1 MW to 5 MW and an additional 20 MW for PV projects exceeding 5 MW in size. The last two project typologies will likely compete in the upcoming mixed wind-solar auction for projects over 1 MW.

Poland’s cumulative installed PV capacity reached around 300 MW as of the end of May. According to another report from the IEO, an installed PV capacity of around 1.2 GW may be reached by the country at the end of 2020, as a result of the deployment of all of the aforementioned auctions. Most of the country’s current installed PV power, the IEO said, is represented by residential and commercial PV projects developed under the expired green certificate scheme and net metering for solar up to 40 kW.

Piotr Pająk represents Polish renewable energy portal Gramwzielone.pl.Greenpeace Polska



Source PV Magazine

Click to comment

Leave a Reply

Your email address will not be published. Required fields are marked *

More in Solar

Categories

September 2018
M T W T F S S
« Aug   Oct »
 12
3456789
10111213141516
17181920212223
24252627282930

Follow

Subscribe to notifications
To Top
%d bloggers like this: