Uncertainty and challenges in Jordan’s Round 3 RE auction

Solar

Uncertainty and challenges in Jordan’s Round 3 RE auction



Changes to Jordan’s Round 3 renewable energy auction will mean just 150 MW of capacity will be allocated for PV projects, down from 200 MW. Meanwhile, the government has accepted all 16 of the technical bids submitted in April, meaning it now hangs on price. The final results are expected soon.

In December 2016, Jordan’s government opened bids for a tender totaling 200 MW of new large-scale solar PV, and 100 MW of new wind, capacity. However, it has now reduced these to 150 MW, and 50 MW, respectively.

In a statement to the official national news Agency, Minister of Energy and Mineral Resources, Hala Zawati, said that 100 MW of the 300 MW originally assigned to Round 3 projects will now instead be assigned for industrial PV projects. This will leave Round 3 with just 150 MW capacity for up to three PV large-scale projects, and 50 MW for one wind project.

The government has also said this week that all of the 16 technical bids submitted under Round 3 in April, have been approved, meaning the winners will now be selected on price. The final results are expected to be published in the coming weeks.

The bidders include: Voltalia SA; Solarpack Corporación Technológia, S.L; ACWA Power; First Solar International Middle East FZ-LLC; Neon SAS; Hanwha Energy Corporation; Jinko Power (HK) Company Limited; and Canadian Solar UK Projects Ltd.

The last winning projects selected in Round 2 in 2015, reached a record-low price of US$0.0613/kWh. For this round, it will be interesting to see if prices will make it below the $0.03/kWh threshold, as was seen in the recent solar tender in Egypt.

The new projects will be located in Ma’an south of Jordan, which has favorable solar irradiation conditions and relatively mild temperatures, making it ideal for PV technologies. Successful bidders will be offered a power purchase agreement for a term of 20 to 25 years.

Setbacks

Jordan has made remarkable progress in the field of renewable energy over the past few years. Since 2012, the year that marked Renewable Energy law enforcement, 961 MW of solar and wind have already been connected to the grid, or are under construction, covering slightly more than 20% of the capacity needs of the small Middle Eastern country, according to the National Electric Power Company’s 2017 annual report.

Despite the advancements, the industry has started to slowdown, due to the technical limitations of the grid. The government’s proposal to add in 35% domestic content requirements, announced in April, has also suffered many set-backs. This, combined with the reduced tender capacity, has impacted growth, and leaves open questions about the attractiveness of, supposedly, the most mature market in the region.

By Amjad Kashman



Source PV Magazine

Click to comment

Leave a Reply

Your email address will not be published. Required fields are marked *

More in Solar

Categories

September 2018
M T W T F S S
« Aug    
 12
3456789
10111213141516
17181920212223
24252627282930

Follow

Subscribe to notifications
To Top
%d bloggers like this: